Thursday, December 17, 2015

Master Dave: part 8

The Rock: Part Eight
So, as Julie just wrote, she and Rog have been inundated with decisions about things which most of us don’t think about or take for granted—location of lights and switches, which way should the door swing, etc.  We were asking questions to avoid the “oops” moments later. 
For instance:  what are you doing for a vanity mirror? Julie wanted two mirrors, both centered over their respective sinks.  Lighting was going to be two sconces on either side of each mirror.  Following the plan, we would have ended up with room for three and a half sconces in order to maintain the centering and spacing. Solution was to plan on moving the vanities down the wall a bit, and building the wall a few inches longer to accommodate the move, not a big deal at all right now, but virtually impossible later. I think Bruce caught that one, but brainstorming leaves us all exhausted and wondering where the solution came from.
Probably the hardest thing for both Julie and Roger was to deal with the myriad of decisions Jason, our electrician from WER Electric (shameless plug), needed to fully customize each room for their particular needs—a difficult task considering they’ve never lived in the house.  “Is the couch going here…or here? ‘Cause I need to put a floor outlet in, and then there’s the lighting…and did you want one or two switches controlling these lights?  I can separate them, y’know.  Or did you want a remote, I can put it here…”  They both looked over at Bruce and I several times, and we just giggled, and shrugged.
We are officially in the rough-in stage, and we should be done with the framing, but we are not, so each trade can only go so far until we rush over, stick a wall up then sprint to the next place.  There were lots of time-consuming details associated with the structural beams, and have been playing catch up ever since.  I think today, the 15th, we’ll have all the walls up and done.  The plumbers look to be done having located a new drain for the kitchen and completely new everything in the bathroom.  Jason’s guys have pulled more than 5000 feet of new wire in replacing everything upstairs and adding what I just head counted as 40 recessed cans—I’m probably off b y a few. The mechanical guys have a few details to complete, but…
We’re hoping to call for inspections tomorrow, but it’s snowing like crazy out there, so it’s hard to say who will show up and when.
NOTE: Inspections have been called for today, the 17th BUT we were looking at the drywall in the bedroom and thought it a good idea to remove it—there were cracks and holes and hey, let’s just start off anew, do a little prep for the drywall sub, etc.  We immediately found the reason for the cracks: whoever installed the bay windows (and I’m going to hunt you down) decided that headers weren’t that important, so they cut part of the original 2 x 12 header at the door and cobbled in a 2 x 6 header across the window.  Then they “forgot” to nail it to a stud, so there’s essentially nothing holding up a five foot section of ceiling and roof except drywall.  And, I guess if you’re going to go to that kind of trouble, you should bury a junction box in the wall by taping it over and pretending it was never there.

We’ll try to fix that this morning, before the inspector shows up—it’s a gray area for the inspector as it’s nothing we’ve touched or done, and therefore not subject to his review, but it’s not right and we all know it. And it’ll give us a chance to dismember the other bird’s nest right next to the framing gaffe.  It’s a big one!